The First-tier Tribunal has made remediation contribution orders totalling £46,500,650 against five respondents connected with seven Manchester buildings. It examined relevant defects, reasonable remediation expenditure, corporate association and whether an order was just and equitable under section 124 of the Building Safety Act 2022.
What happened?
In Secretary of State for Housing, Communities and Local Government v Urban Splash Ltd and others [2026] UKFTT 1426 (PC), decided on 5 November 2026, the tribunal considered seven residential buildings developed between approximately 2000 and 2008. Fire-safety remediation had cost more than £60 million, substantially supported by the Building Safety Fund.
The tribunal determined that £60,638,548 had reasonably been or would be incurred in connection with relevant defects. It ordered five respondents to pay a total of £46,500,650, jointly and severally, predominantly to the Secretary of State and in part to a management company. Orders were not made against other respondents.
What does association mean?
Association with a developer is not automatic liability. The tribunal considered the statutory criteria and whether an order was just and equitable against each respondent. The extent and nature of the connection with the developer, the buildings and the wider enterprise were relevant.
The decision is therefore important for developers, group companies, investors and those managing historic portfolios. It is not authority for saying every member of a corporate group will be liable whenever a developer faces remediation costs.
Why was there a 10% reduction?
The tribunal made a case-specific 10% adjustment to certain publicly funded remediation expenditure after examining government responsibility for historic regulatory shortcomings. It expressly said this was not a finding that government caused 10% of the defects and not an apportionment of causative responsibility. No general 10% discount follows for other cases.
What should businesses do now?
- Map buildings, developer entities, associated companies and historic corporate restructurings.
- Preserve design, construction, compliance and fire-safety records for potentially affected buildings.
- Separate actual and proposed remediation costs; retain procurement, scope, funding and cost evidence.
- Review how the statutory just-and-equitable test may apply to each proposed respondent, rather than assuming group-wide liability.
- Check the relevant tribunal orders and any appeal or stay before acting on payment deadlines.
What happens next?
The orders recorded in the decision required payment by 4pm on 3 December 2026, subject to any later procedural developments. Anyone directly involved should obtain up-to-date advice on the orders and any appeal position.
Verifiable sources
Need advice on a live matter?
HQ Law advises construction and engineering businesses on construction contracts, adjudication, building defects, payment issues and associated commercial disputes. If you are dealing with a live matter, get advice on the relevant documents and deadlines.
This article provides general information only and is not legal advice on any particular contract, project or dispute.