Record exactly when the Notice was received, obtain the contract and amendments, identify the dispute said to have crystallised, check the adjudication/appointment mechanism, preserve any jurisdiction objections, and begin a focused evidence chronology. Under section 108 of the Construction Act, the procedure must aim to secure appointment and referral within seven days of the Notice, with the decision ordinarily due 28 days after referral.
Why the first 24 hours matter
Statutory construction adjudication is deliberately fast. The legal and factual issues may be substantial, but the procedural timetable is compressed. Early decisions about jurisdiction, document control and who will prepare the factual and technical evidence can therefore affect the whole response.
The key point is not to produce a full defence on day one. It is to prevent avoidable mistakes while creating a reliable route to the response.
1. Preserve the Notice and prove when it was served
Keep the Notice of Adjudication in the form in which it arrived, including the email, delivery metadata or other evidence of service. Record the date and time. Service can affect the appointment and referral timetable and may also be relevant to jurisdiction.
Under the Scheme for Construction Contracts, the Notice should briefly identify the nature of the dispute, where and when it arose, the redress sought and the parties. The actual contractual adjudication provisions may differ, so both the Notice and the contract need to be read together.
2. Obtain the complete contract, not just the order form
Locate the signed contract, order, subcontract, schedules, amendments, incorporated standard terms and any later agreements that changed the dispute-resolution mechanism. Construction contracts are frequently assembled from several documents. The adjudication clause and the substantive provisions relevant to the dispute may be in different places.
If there is an argument about whether a construction contract exists, what terms were incorporated, or which adjudication procedure applies, that can become a jurisdiction issue.
3. Identify the dispute that had crystallised before the Notice
Adjudication is not simply a mechanism for presenting a new claim for the first time. The scope of the dispute referred matters. Pull together the claim, response, payment notices, correspondence and meeting records that show what had been asserted and rejected or not admitted before the adjudication started.
Do not assume the description in the Notice is necessarily the final word on scope. Compare it with the dispute that had actually developed between the parties.
4. Check appointment and referral deadlines immediately
Section 108 requires the contractual procedure to provide a timetable with the object of securing appointment of the adjudicator and referral within seven days of the Notice. The adjudicator must ordinarily decide within 28 days of the referral; the referring party can consent to an extension of up to 14 days, and both parties can agree a longer period.
Under the Scheme, the referral is to be sent not later than seven days after the Notice and should be accompanied by the contract and the documents on which the referring party relies.
5. Preserve jurisdiction objections without derailing the merits response
Potential jurisdiction issues may include whether the adjudicator was appointed under the correct procedure, whether there is a qualifying construction contract, whether the dispute had crystallised, whether the adjudicator is being asked to decide something outside the dispute referred, or whether the same dispute has already been decided.
A respondent should take advice on how and when to reserve its position. Simply raising the word “jurisdiction” is not a substitute for identifying the actual objection, and a jurisdiction strategy should not prevent preparation of the substantive response.
6. Build a response file around the issues, not around the project archive
Start with an issue list. For each issue, identify the contractual provision, key fact, supporting document, witness, valuation/time consequence and the referring party's position. This is usually more useful than uploading thousands of project emails and hoping the answer can be found later.
Typical priority records include payment applications and notices, valuation sheets, programmes, instructions, variation records, meeting minutes, contemporaneous site records, expert/consultant material and the correspondence by which the dispute crystallised.
7. Decide what not to do
- Do not make substantive admissions in hurried correspondence simply to appear responsive.
- Do not abandon a possible jurisdiction point without considering it.
- Do not assume a later extension will be granted.
- Do not send uncontrolled volumes of confidential material before the legal team has identified what is relevant.
- Do not allow commercial negotiations to distract from the formal adjudication timetable.
Quick questions
How long does a UK construction adjudication take?
The statutory default is a decision within 28 days of referral, subject to a possible 14-day extension with the referring party's consent or a longer period agreed by both parties.
Can a respondent ask the court to decide jurisdiction before the adjudication finishes?
Sometimes. The 2026 TCC Guide recognises urgent Part 8 applications for declaratory relief in appropriate cases, including genuine disputes about an adjudicator's jurisdiction. Whether that is proportionate or suitable is fact-specific.
Does receiving a Notice mean HQ Law should immediately receive the entire project archive?
No. The first task is a conflict check and a concise understanding of the parties, contract, Notice, deadline and dispute. The relevant evidence can then be requested in a controlled way.