When installed construction products fail, a contractor must identify who supplied what, when, on which terms and with what evidence. Limitation and court deadlines may need immediate attention even while the upstream claim is still being investigated.
The dispute
In Loughton Contracts PLC v The Amtico Company Ltd [2026] EWHC 2814 (TCC), handed down on 3 November 2026, flooring installed on residential developments at Wembley Park had failed. The main contractor was holding the flooring installer responsible for replacement costs alleged at approximately £2.9 million, although the main contractor had not then issued proceedings against the installer.
The installer had issued protective proceedings against the product supplier. It had not served particulars of claim by the original deadline. A temporary stay had been ordered, and the parties then disputed whether to extend that stay or strike out the claim. The judgment examined procedural defaults alongside disputed substantive supply and liability issues.
Outcome: Constable J refused Amtico’s applications for summary judgment and strike-out. The court granted Loughton relief from its failure to serve Particulars of Claim on time, but declined to extend the stay for a further six months. This did not determine whether Amtico was ultimately liable for the flooring defects.
The case is an important reminder that filing a claim form or obtaining a stay does not remove the need to comply carefully with the court’s orders and relevant Civil Procedure Rules.
Evidence that can determine a supplier claim
Purchase orders, order acknowledgements, delivery tickets, invoice references, site logs, batch identifiers and installation records may point to different delivery dates and contract terms. Each matters when establishing which product was used, contractual obligations, any agreed limitation of liability, and when a cause of action accrued.
Amtico faced serious evidential difficulties over its terms. The relevant terms were generally appended to invoices after order confirmation. Invoices produced in evidence were later reprints marked “DUPLICATE”, and the terms did not match the versions initially relied upon. The court considered the precise terms unresolved. Even assuming incorporation, Amtico served no evidence that the exclusion clauses satisfied the reasonableness requirement under the Unfair Contract Terms Act 1977, for which it bore the burden of proof under section 11(5).
Supplier conditions may vary between transactions. Do not assume the terms attached to a later invoice governed an earlier order; trace offer, acceptance and incorporation for each relevant purchase.
Practical steps after a product failure
- Preserve product samples, photographs, expert evidence and the installation methodology before replacement works alter the evidence.
- Match each affected area against product batch, purchase order, invoice and delivery docket.
- Collect supplier terms, specifications, warranties and all alleged exclusions or caps.
- Map potential contractual, tortious and statutory causes of action and obtain advice on limitation dates promptly.
- If protective proceedings are needed, maintain a court-deadline tracker; a stay is not a substitute for procedural compliance.
Do not confuse responsibility with remedy
Proof that a product failed does not by itself establish a recoverable claim for the entire replacement cost against its supplier. Causation, workmanship, contractual risk allocation, mitigation and the reasonable remedial scheme will all need examination. The merits depend on the actual contract and evidence.
Verifiable sources
Need advice on a live matter?
HQ Law advises construction and engineering businesses on construction contracts, adjudication, building defects, payment issues and associated commercial disputes. If you are dealing with a live matter, get advice on the relevant documents and deadlines.
This article provides general information only and is not legal advice on any particular contract, project or dispute.