Short answer

A construction settlement does not necessarily settle every future or potential claim arising out of the same project. The answer depends on the objective meaning of the release, the claims then in issue and the surrounding context. A later claim may still face limitation, abuse-of-process and evidential objections.

What did the TCC decide?

In United Living (South) Ltd v Dovista UK Ltd and others [2026] EWHC 2676 (TCC), handed down on 3 November 2026, the court considered a later claim by a design-and-build contractor against an architect following earlier proceedings and settlement arrangements concerning the same development.

Mr Justice Eyre held that the settlement agreement in question compromised the claims live in the earlier proceedings, not the distinct claims now pursued. The court also rejected the argument that bringing the later proceedings amounted to an abuse of process in the circumstances. It dismissed the relevant defendant’s application.

This was a fact-specific interpretation of a particular agreement. It is not a general rule allowing parties to keep claims back or to ignore finality wording in settlements.

Why do emerging defects make settlement difficult?

A building may have several unrelated defects, or one defect may point towards wider design or installation failures. A party negotiating a settlement needs to distinguish problems already pleaded, defects identified during investigations and further risks which have not yet been fully assessed.

Broad wording releasing all claims ‘arising out of’ the works may be intended to achieve greater finality than wording confined to specified defects or proceedings. Neither form should be assumed to have a particular effect without reviewing the full agreement and context.

What should construction businesses do?

  1. Before settlement, create a short defects matrix identifying the alleged failure, location, responsible parties and evidence available.
  2. Identify known but unquantified issues and record whether the settlement is intended to cover them.
  3. Review release wording, reservations of rights, non-parties, insurers and connected professional appointments.
  4. Consider whether additional investigation is needed before a full-and-final compromise.
  5. Check relevant limitation periods and avoid assuming that settlement negotiations preserve rights.

What remains uncertain?

The effect of any other release turns on its wording and context. A later action might still fail on limitation or merits even if it is not barred by the first settlement. The court’s rejection of abuse in this case should not be treated as permission to split claims strategically.

Verifiable sources

Need advice on a live matter?

HQ Law advises construction and engineering businesses on construction contracts, adjudication, building defects, payment issues and associated commercial disputes. If you are dealing with a live matter, get advice on the relevant documents and deadlines.

This article provides general information only and is not legal advice on any particular contract, project or dispute.