Short answer

The Building Safety Regulator (BSR) has published updated building-control approval data covering August to October 2026, with the underlying dataset stated to be current as at 1 November. The figures suggest progress for some higher-risk building applications, but do not provide a reliable completion date for an individual project. Developers and contractors should distinguish regulatory approval from contractual completion obligations, and check their contracts before assuming that a Gateway 2 delay automatically gives an extension of time or additional payment.

What the new figures show

For new higher-risk buildings and conversions, the BSR reported a 95% approval rate across the latest rolling 12-week period, based on 40 approvals out of 42 decisions, and a median approval time of 20 weeks. For external remediation applications, the corresponding figures were a 93% approval rate and a median approval time of 32 weeks. For category A and B internal work on higher-risk buildings, the approval rate was 91% and median approval time 30 weeks. These are observed statistics for decided applications, not statutory deadlines or promises as to the processing time of a new submission.

The 20-week median should be read against regulation 5 of the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023: for a valid new higher-risk building application, the normal determination period is 12 weeks, unless the applicant and regulator agree a longer period in writing. The statutory period is not the same measure as the published median of completed approvals, but the gap is significant for programme planning.

The levy-related application surge

The report records 64 new-build applications in September, up from 34 in August, followed by 6 in October. The BSR attributed the September increase to applications ahead of the Building Safety Levy taking effect on 1 October 2026. Its published snapshot identified 41 applications received on or after 21 September for enhanced validation. Of those, 18 had been assessed as poor quality and placed on pause by agreement with applicants; a further eight were recommended for rejection but remained subject to final review; nine were still undergoing enhanced validation. These were positions reported as at 1 November, not final outcomes for every application.

Why the figures matter commercially

A project may depend on the approval sequence for mobilisation, commencement, variations or occupation. Long approval periods can generate delay-related discussions over preliminaries, plant, subcontractor availability, design changes, finance costs and the date on which works can lawfully proceed. Those consequences will not always sit with the same party. The outcome depends on the contract, who is responsible for each application, the state of the submission, causal links to the programme and whether the relevant notices were given.

The overall 32-week median for external remediation includes older, difficult cases. The BSR says newer remediation applications submitted in 2026 are progressing in approximately 22–26 weeks, with an approval rate of around 90%. Neither figure should be treated as an assured timescale for a particular submission.

Application quality is a project risk

The BSR data emphasises that poorly prepared submissions may be held for clarification or paused. Project teams should maintain a single controlled schedule of design information, dutyholder responsibilities, fire and structural safety evidence, third-party dependencies, and outstanding BSR questions. A programme that assumes approval immediately after submission, without allowance for validation and information requests, is vulnerable to disruption.

What to do now

Update the master programme using a range of regulatory scenarios rather than the published median alone. Identify the person contractually responsible for preparing and responding to each application. Keep a dated record of submission, validation, regulator queries, design revisions and responses. Review relevant JCT or NEC change-control and delay-notification provisions before a problem crystallises. Where a scheme was submitted close to 1 October 2026, verify its actual validation and levy position rather than relying on general assumptions. For impending completion, check the separate Gateway 3 requirements and do not treat Gateway 2 permission as authority to occupy.

A data update, not a legal relaxation

The figures describe administrative performance. They do not change the Building Safety Act 2022, the Building (Higher-Risk Buildings Procedures) (England) Regulations 2023 or the approvals that apply to a particular project. The BSR’s eligibility summary is simplified; the statutory definitions and any exclusions must be checked when deciding whether a particular building or work falls within the higher-risk regime.

Need advice on a live matter?

HQ Law can advise on the contractual treatment of regulatory delay, change control, responsibility for applications and resulting construction disputes. Early review is particularly useful where notices or programme decisions cannot wait.

This article is general information based on the BSR dataset published on 6 November 2026 and updated on 11 November 2026. It is not legal advice for any individual project.