Before starting adjudication, check that the company bringing the claim still owns the relevant contractual rights. In Scot Frame Timber Engineering Ltd v JAT Construction Ltd [2026] EWHC 2892 (TCC), handed down on 11 November 2026, HHJ Kelly, sitting in the Technology and Construction Court, dismissed an application for summary judgment enforcing two adjudication decisions. The defendant had realistic prospects of defending enforcement on grounds including an earlier business transfer, the scope of the first referral and the treatment of evidence in the second adjudication. Importantly, this was a summary judgment decision, not a final trial of those defences.
What happened
Scot Frame and JAT entered a JCT Minor Works contract for timber-frame works in North Wales. After disagreement over defective or incomplete work and access to site, Scot Frame pursued adjudication. A first decision in June 2023 assessed the value of work at £402,500, leaving a stated £155,500 due after payments already made. A later adjudication concerned a payment notice, a valid pay less notice and the extent to which JAT could rely on a fuller defects case supported by new expert evidence. Meanwhile, an intra-group business sale agreement dated 31 December 2021 had transferred assets and contractual interests to another Saint-Gobain group company. JAT relied on that agreement to challenge Scot Frame’s entitlement to commence the adjudications.
An assignment can affect the right to adjudicate
The contract restricted assignment without the other party’s consent. JAT gave written retrospective consent in April 2026. The court considered it realistically arguable that the earlier agreement had already operated as an equitable assignment and that the contractual benefit, including the right to adjudicate, had passed before the two adjudications were commenced. The judgment does not mean every corporate reorganisation automatically transfers adjudication rights, or that retrospective consent will always be effective. The agreements, the anti-assignment clause, any notice and the parties’ conduct require close examination.
The retrospective consent was important because the court regarded it as realistically arguable that the consent requirement in clause 3.1 protected JAT, as the party obliged to perform, and that JAT could therefore waive the earlier failure to obtain consent. This was not a final finding that the purported assignment was effective.
Define the dispute actually referred
The first adjudication had been framed around an allegation that JAT repudiated the contract by denying site access. Scot Frame later withdrew that allegation but the adjudicator proceeded with valuation issues. The court held that JAT had a realistic argument that the adjudicator had exceeded the jurisdiction conferred by the notice and referral, or that more than one dispute had been referred. This is a reminder that a referral should identify the dispute and remedy clearly, and any later change in case theory should be tested against the adjudicator’s jurisdiction.
Previously raised is not always previously decided
In the second adjudication, the adjudicator accepted that JAT had served a valid pay less notice but declined to examine new expert evidence about defects, reasoning that the matters had already been considered in the first adjudication. The court distinguished an issue that had actually been decided from an earlier claim which had failed because the material then produced did not prove it. It found a realistic prospect of a material natural-justice defence because relevant fresh expert evidence had been excluded. That is a fact-sensitive conclusion; it does not create an unrestricted right to relitigate points that have already been determined.
Payment of an adjudicator’s fees does not necessarily amount to accepting liability under the decision. JAT had paid its share of the fees, but the court considered it realistically arguable that the correspondence, taken as a whole, preserved its objection to the principal sum. Anyone paying fees while disputing enforcement should reserve that position clearly and contemporaneously in writing.
What construction businesses should do now
Before commencing adjudication following a sale, restructuring or group transfer, obtain the asset-sale agreement and check precisely who holds the contractual claim and adjudication right. Map the notice of adjudication, referral and relief sought so that the dispute referred remains clear. If relying on a previous adjudication, separate findings actually determined from claims rejected for lack of proof. Where a pay less notice and defects evidence are central, present the evidence in an organised manner and ensure any jurisdiction or natural-justice objection is reserved promptly. Seek advice before assuming that payment of an adjudicator’s fees has waived every objection.
Need advice on a live matter?
HQ Law advises contractors, subcontractors and employers on adjudication strategy, payment notices, jurisdiction objections and enforcement. These issues can move quickly, so early document review is important.
This article concerns the judgment as reported on 11 November 2026 and is general information, not legal advice on a particular contract or adjudication.
Verifiable sources
- Scot Frame Timber Engineering Ltd v JAT Construction Ltd [2026] EWHC 2892 (TCC), approved judgment, 11 November 2026 (court-approved copy hosted by Davies & Davies; an official Find Case Law or BAILII version was not located at review)
- Davies & Davies, case summary, 11 November 2026 (secondary cross-check)